Dunmaglass planned crane deliveries Fri 7 Oct

Following the note we sent out on Friday the Police have now confirmed that they are able to escort the undelivered turbine components to site this week. The turbine blades and tower sections will be escorted by the police and they will leave from Inverness Harbour and turn on to the A9 via the Longman Roundabout. They will then turn off the A9 on to the B851 and travel to the site entrance.  The turbine deliveries are being transported by road from Inverness with a police escort.

The police escort will ensure the safe movement of these large delivery vehicles throughout their journey.

Day

Approximate time of arrival on the B851

Approximate time of arrival at site entrance

Friday 7 October 9.30am 11.00am
Friday 7 October 12.30pm 2.00pm
Friday 7 October 3.30pm 5.00pm

Please note these times are subject to variation at short notice and will depend on weather or traffic conditions.

*Please note this delivery is travelling from Hamilton rather than Inverness meaning it will be potentially subject to more variation than the other loads.